June 2010:  Gulf of Mexico Industry Review

 

  

 

June 28, 2010

 

Rig Utilization

 

Mobile rig utilization in the Gulf of Mexico fell for the week as two previously working rigs came off contract.  Total fleet utilization is now 57.4% with 70 of 122 mobile rigs under contract or committed for work.  Marketed utilization, which excludes those cold stacked and other non-marketed rigs, fell to 83.3% with 70 of the 84 units under contract.  Atwood Oceanics submersible Richmond completed its contract for Contango Operators and was moved to Sabine Pass. 

 

As reported above, one jackup was released, which drove fleet utilization down to 47.6%, now with 39 of 82 units under contract or committed for work.  Marketed utilization dropped to 78% with 39 of 50 units contracted.  The Hercules 204 accounted for the decrease after it finished its contract with LLOG Exploration.

 

Floating rig fleet utilization remained at 91.2% with 31 of 34 units under contract, while marketed utilization was also unchanged at 93.9% with 31 of 33 units under contract.

 

Total platform rig fleet fell to 31.4% with 16 of 51 rigs contracted, while marketed utilization dropped to 45.7% with 16 of 35 rigs under contract.  Inland barge fleet utilization fell slightly.  Total fleet utilization is now 48.3% with 28 of 58 units under contract, while marketed utilization is 70% with 28 of 40 units under contract.

 

Headline News

 

New Orleans U.S. District Judge Martin Feldman refused to put on hold his ruling which blocked the federal government from enforcing its recently imposed six-month deepwater drilling moratorium.  It is expected that the Obama administration will take its case to the U.S. Court of Appeals for the Fifth Circuit in New Orleans.  In the meantime, U.S. Interior Secretary Ken Salazar announced he would take a look at issuing a new, scaled-back moratorium “in the weeks and months ahead”.  Despite the good news for the industry, it is not expected that any operators will resume drilling operations, but will instead wait until all the court battles are over.

 

The National Oceanic and Atmospheric Administration has suspended daily production of offshore BP’s oil spill trajectory maps because a change in ocean currents has minimized impact risks to the Florida Keys and most of the Florida peninsula.

 

Operator News

 

Exxon Mobil Corporation has completed its merger agreement with XTO Energy, Inc. The new organization will continue to be known as XTO Energy, Inc. and maintain its headquarters in Fort Worth, Texas.  Jack Williams, a former Vice President of ExxonMobil Development Co., has been elected President of XTO and Keith Hutton, formerly XTO’s Chief Executive Officer, is Executive Vice President of the new organization.

 

Gulf Coast Western confirmed an oil and gas discovery  in their Opelousas field in St. Landry Parish, LA.   Flow tests resulted in a production rate of approximately 672 bopd and 3.2 mcf/d.

 

BP reports that two systems continue to collect oil and gas flowing from the Deepwater Horizon’s failed blow-out preventer (BOP) and transport them to vessels on the surface. Meanwhile, rough seas expected from Tropical Storm Alex could set back BP's efforts to increase subsea oil collection capacity at the gushing Macondo well by about a week, but should not interrupt current collection methods or drilling operations for two relief wells.

 

Driller News

 

Noble Drilling has entered into an agreement to acquire Frontier Drilling in an all cash transaction of $2.16 billion.  The sale, which is expected to close by the end of July, will add a total of six floating drilling units to Noble’s fleet.  Frontier’s fleet consists of three DP drillships, including two Bully-class joint venture-owned rigs under construction, two conventionally moored semis and one DP FPSO vessel.  The joint venture-owned Bully class drillships, currently under construction in Singapore, are Arctic-capable and rated to drill in up to 12,000 fsw.  The rigs, which are owned 50/50 by Frontier and Royal Dutch Shell, have firm five and ten year contracts respectively with Shell and both are slated to begin operations in 2011.  In the U.S. Gulf, Frontier currently has the semi Frontier Driller under contract with Shell to mid-May 2012 at a day rate of $383,000.  The purchase will add some 23 rig years of contracts generating approximately $3.2 billion in gross contract backlog ($2.0 billion net to Noble).  As part of the deal, Noble will assume Frontier’s remaining construction obligation, including around $311 million of Frontier’s construction costs for the Bully I and Bully II drillships.  In addition to the Frontier purchase, Noble has also inked several new agreements with Shell.  The parties signed a contract for newbuild drillship Noble Globetrotter, with operations to begin in the second-half of 2011.  During the first five years of the contract, Shell will pay a day rate of $410,000, and then go to a market index for the second five years.  The rig will also be eligible for a 15% performance bonus.  Shell also agreed to take a second Noble ultra-deepwater drillship to be built and delivered in the second-half of 2013.  Noble expects construction costs or the rig to be around $550 million, exclusive of capitalized interest.  Contract terms will be the same as those for the Noble Globetrotter, and the rig will have identical operational capabilities.  Shell also inked a deal to extend its contract for semi Noble Jim Thompson for three years starting in March 2011.  Currently at a day rate of $505,000, Noble will reduce the current rate to $336,200 upon closing of the Frontier purchase for the remainder of the current term, with the rate remaining there for the extension period.  Finally, Shell and Noble have reached an agreement, effective immediately, to address the deepwater drilling moratorium.  The agreement allows Shell to suspend contracts on rigs currently drilling or scheduled to drill here during the restrictive period.  Shell will, however, pay a reduced standby rate, essentially covering Noble’s operating costs.  The term of the contracts will be extended for a period equal to any drilling suspension time at the original contract rate.  The agreement will affect the Noble Jim Thompson, Frontier Driller (upon purchase) and newly-delivered Noble Danny Adkins.  The Noble Jim Thompson is currently headed to Signal Shipyard for upgrades, while the Danny Adkins has been undergoing acceptance testing.  It is believed that Noble may have a permit in place shortly for the rig to do some workover and completion work in the Alaminos Canyon area.  Noble also renegotiated its contract for with Noble Energy to restructure its deal on semi Noble Clyde Boudreaux.  Under terms of the deal, Noble will receive a standby rate of $145,000 effective from June 15 to December 12, with an option to extend should the drilling moratorium last longer than six months.  In addition, both parties have agreed to “negotiate in good faith” to replace the original drilling contract at a dayrate of $397,500 following the standby period.  The term of the new contract will be equal to the 17 months remaining in the original contract term which would have ended in November 2011.  The original two-year contract was at a dayrate of $605,000.  The move is seen as a positive as the rig would have likely been at a $0 day rate during the moratorium period, while at the same time allowing Noble Energy to possibly declare force majeure on the contract, a road neither company likely would have wanted to go down.  While others are likely to follow suit and reach similar agreements, the only question is which operators will be willing and/or able to pay a standby rate for period that could last six months or more.

 

Rowan newbuild jackup Rowan EXL II has an agreement in place with BP for a three-year contract off Trinidad starting in October.  Construction on the rig is expected to be completed in September, with the new contract beginning in October.  The rig is now next available in November 2013.  Rowan also says Apache has declared force majeure on its contract with jackup Cecil Provine.  The rig is on location in Grand Isle 40, but has been waiting on permit approval.  Rowan is currently weighing its options to determine what its response will be.  Apache also has jackup Bob Palmer under contract for work in High Island A-376, but is waiting for permit approval for the work to begin.  The Rowan Louisiana continues to standby in Sabine Pass for McMoRan E&P to secure its permit for a 180-day well in Eugene Island 26.

 

Hercules Offshore completed its contract with LLOG Exploration and has hot-stacked jackup Hercules 204 in South Timbalier 32.  Hercules is expected to have contracts for  jackups Hercules 201 and Hercules 205 end shortly, and it is not believed the company has follow-up work in place.

 

Jackup ENSCO 68 is now rigged up on location in Main Pass 298 for Chevron, but work has not yet begun until the permit is secured.  ENSCO’s contract with Chevron was originally scheduled to begin in early June, but leg delays in completing leg repairs, followed by the new permitting requirements have delayed start of the work.

 

Atwood Oceanics submersible Richmond completed its ADTI turnkey for Contango Operators in Eugene Island 10.  The rig just arrived in Sabine Pass where it is undergoing regulatory work.  Its next contract with Rooster Petroleum has been delayed as Rooster does not yet have its permit secured.  That work was for a 40-day well in Eugene Island 28.

 

Seahawk Drilling says it has about a week remaining on its contract with Peregrine O&G with jackup Seahawk 2600.  Peregrine had an option well in the Galveston area, but it will not be exercised due to the current permitting issues.  The rig is currently working for Peregrine in North Padre Island 975.

 

Service/Supply News

 

FMC Technologies, Inc. has signed a four-year subsea manifold frame agreement with Petrobras, The award is expected to result in approximately $300 million in revenue to FMC Technologies if all of the subsea equipment included in the agreement is ordered.

 

J. Ray McDermott announced it was recently awarded a contract to upgrade a single point mooring system for Reliance Industries, Ltd. off the coast of Hazira, India.

 

June 21, 2010

 

Rig Utilization

 

Mobile rig utilization in the Gulf of Mexico rose this week as one semi went idle, offset by a return to contracted for two jackups previously counted as idle.  Total fleet utilization is now 59% with 72 of 122 mobile rigs under contract or committed for work.  Marketed utilization, which excludes those cold stacked and other non-marketed rigs, is virtually unchanged at 85.7% with 72 of the 84 units under contract. 

 

Within the jackup fleet, two units previously counted as idle were returned to the contracted rolls.  That pushed overall utilization up to 48.8% with 40 of 82 units under contract or committed for work.  Marketed utilization also rose to 80% with 40 of 50 units contracted.

 

Floating rig fleet utilization fell to 91.2% with 31 of 34 units under contract, while marketed utilization also dropped, coming in at 93.9% with 31 of 33 units under contract.

 

Total platform rig fleet increased to 39.2% with 20 of 51 rigs contracted, while marketed utilization rose to 52.6%, with 20 of 38 rigs under contract.

 

Inland barge fleet utilization also rose.  Overall utilization is now 50% with 29 of 58 units under contract, while marketed utilization is 72.5% with 29 of 40 units under contract.

 

Headline News

 

Floating rigs continue to reach "safe stopping points" and move to stack locations.  Diamond Offshore semi Ocean Voyager is now in West Cameron 184 after finishing up with Walter O&G in Ewing Bank 834.  Also, semi Transocean Amirante secured its well for Eni Petroleum in Green Canyon 254 and has been moved to a standby location in Mobile. Noble Drilling says the Noble Clyde Boudreaux finished operations in Green Canyon 723 for Noble Energy and moved to High Island 66, where it joins hot stacked Noble Paul Romano.  Meanwhile, Noble will move the Noble Amos Runner to nearby High Island 94.  Finally, the contractor says that newbuild semi Noble Jim Day departed Singapore on June 15 enroute to the Gulf of Mexico.  The rig will stop around Trinidad, be offloaded from the heavyift vessel and undergo thruster installation before heading on to the Gulf.  The rig is scheduled to begin a four-year contract with Marathon Oil in September.

 

Following in Noble Drilling's footsteps, Transocean now says it does not believe the deepwater drilling moratorium constitutes the force majeure claim recently made by Anadarko on its contract with drillship Discoverer Spirit, under contract at $482,000/day until October of 2013.  The company also has commented in regards to the force majeure recently made by Statoil on drillship Discoverer Americas.  Transocean says if the contract is canceled, it is then owed the remaining value of the contract, which runs to October 2013 at a day rate around $475,000.  Statoil also declared force majeure on its contract with Maersk Drilling semi Maersk Explorer, but no word yet from Maersk regarding the claim.  The rig has been working in Walker Ridge 543 and is under contract to mid-September 2013 at a day rate of $450,000.  Meanwhile, Pride International says it does not expect BP to cancel contracts on two newbuild drillships as the contracts are for international use, and the company also believes the deepwater drilling moratorium is not justification for force majeure.   The first unit, the Deep Ocean Ascension, recently arrived in the Gulf and is now undergoing acceptance testing in Galveston.  It is scheduled to begin a five-year contract in the third quarter.  In general, while announcements have not been made, it is believed that most operators with deepwater rig contracts in the Gulf have either declared force majeure or have given notice that they intend to declare.  Given the dollar amounts involved in these contracts and the push back from the drilling contractors, it would not be surprising to see several of these disputes end up in court.  Should that occur, it will likely be some time before final disposition of these contracts is determined.

 

Operator News

 

Cobalt International, Inc. has named John P. Wilkirson as Chief Financial Officer and Executive Vice President, replacing Rodney Gray.  Wilkirson previously served as Cobalt’s Vice President of Strategic Planning and Investor Relations.

 

Driller News

 

Leg repairs to Rowan jackup Bob Palmer have been completed and the rig is now waiting in High Island A-323 for Apache to secure its permit for work in High Island A-376.  The rig has a 90-day plus 90-day option contract with Apache.  Meanwhile, jackup Rowan Louisiana is waiting on McMoRan E&P to receive permit approval for its well in Eugene Island 26.  Once that occurs, the rig will move to location where drilling is scheduled to last 180 days.  Rowan had reported the rig had been cold stacked, but it is now understood that it is merely waiting on the permit situation to be resolved.

 

Nabors Offshore reports several changes to its rig fleet.  First, previously idle platform rig Sundowner IV is now moving to location in Vermilion 365 for the start of a one-well contract with Pisces Energy.  Meanwhile, the company has warm stacked platform rigs Nabors 87 on location for Chevron in Viosca Knoll 786 as well as jackup Dolphin 106.  The rig had recently moved onto Chevron's location in Main Pass 41 for a four-well workover program.  It is understood that permitting delays are at play for the two rigs.

 

Service/Supply News

 

FMC Technologies has been awarded a contract by Statoil for the manufacture and supply of subsea production equipment to support the Pan Pandora field in the Norwegian North Sea.

 

June 14, 2010

 

Rig Utilization

 

Mobile rig utilization in the Gulf of Mexico declined this week. Total fleet utilization is 58.2% with 71 of 122 mobile rigs under contract or committed for work. Marketed utilization, which excludes those cold stacked and other non-marketed rigs, also fell, now standing at 85.5% with 71 of the 83 units under contract.

 

Total jackup utilization decreased to 46.3% with 38 of 82 jackups under contract, while marketed utilization fell to 77.6% with 38 of 49 units under contract. Three jackups went idle due to permitting delays while one previously idle unit received a contract and returned to work.

 

Floating rig fleet utilization this week is 94.1% with 32 of 34 rigs under contract, while marketed utilization is now 96.9% with 32 of 33 units under contract. Drillship Stena Forth departed the Gulf for a drilling program off Greenland. Also, several floaters completed their current wells and have been moved to standby locations, but the contracts remain in effect for now.

 

Within the platform rig fleet, utilization fell slightly with 19 of 51 rigs contracted for utilization of 37.3%, while marketed utilization is 50%, with 19 of 38 rigs under contract.

 

Headline News

 

The Department of the Interior has issued its latest Notice to Lessees (NTL) regarding offshore drilling requirements.  The NTL, which focuses on safety measures, applies to both shallow and deepwater drilling, although the recently announced deepwater drilling moratorium remains in effect.  However, drilling in water depths up to 500 fsw as well as all shallow and deepwater production operations are allowed to continue provided they are in compliance with the new safety requirements.  The Safety NTL implements the seven safety requirements that Secretary Ken Salazar’s 30-day safety report to the President determined could be implemented immediately.  Under the NTL, operators and rig owners must meet the following requirements:

 

- Show certification by the operator’s Chief Executive Officer (CEO) that their companies are operating in compliance with all operating regulations and that they have tested their drilling equipment, ensured that personnel are properly trained and reviewed their procedures to ensure the safety of personnel and protection of the environment.

 

- Provide certification from a Professional Engineer of all well casing and cement design requirements, including that at least two independent tested barriers for the well exists, and adhere to new casing installation procedures before beginning any new drilling operations using either a surface or subsea BOP stack.

 

- Provide independent third-party verification, before drilling any new well, that the BOP will operate properly with the drilling rig equipment and is compatible with the specific well location, borehole design and drilling plan.

 

- Provide independent third-party verification that shows the blind-shear rams are capable of shearing the drill pipe in the hole under maximum anticipated surface pressures.

 

- Adhere to new inspection and reporting requirements for BOP and well control system configuration, BOP and well control test results, BOP and loss of well control events and BOP and loss of well control system downtime.

 

- Before spudding any new well, receive independent, third-party verification of BOP equipment used on all floating drilling rigs to ensure that the devices will operate as originally designed, and that any modifications or upgrades conducted after delivery date of the system have not compromised the design or operation of the BOP.

 

- Have a secondary control system for subsea BOP stacks with remote operated vehicle (ROV) intervention capabilities, including the ability to close one set of blind-shear rams and one set of pipe rams.  The subsea BOP system must have an emergency shut-in system in the event of lost power, as well as a deadman system and an autoshear system.

 

- Conduct ROV Hot Stab Function Testing of the ROV Intervention Panel on subsurface BOP stacks, and provide documentation that the BOP has been maintained according to the regulations.

 

Drilling operations not subject to the deepwater drilling moratorium must fulfill their BOP reporting requirements by June 17 and submit the required safety certifications by June 28 or face a shut-in order.  Additional expanded requirements for exploration and development plans on the OCS will be announced shortly.

 

Operator News

 

Anadarko Petroleum Corp. reaffirmed its full-year 2010 sales-volumes guidance range and projected capital spending. Anadarko's sales-volumes guidance remains 230 million to 234 million barrels of oil equivalent (BOE) for the full year and 57 million to 60 million BOE for the second quarter. Capital spending for the full year is still expected to be in the range of $5.3 billion to $5.6 billion.   The company will reallocate some of the 2010 capital from the Gulf to other areas, including onshore liquids-rich opportunities.
Petsec Energy announced the results of the Main Pass 20 #4 well located in 35 feet of water. The well reached TD 12,800 feet and hydrocarbons were encountered. However, the partners have decided to plug and abandon the well.

 

BP reported the lower marine riser package (LMRP) containment cap continues to collect oil and gas flowing from the MC 252 well.  Meanwhile, preparations for additional planned enhancements to the LMRP cap containment system continue to progress. The first planned addition, to operate in addition to the LMRP cap system, will take oil and gas from the choke line of the failed Deepwater Horizon blowout preventer (BOP) through a separate riser to the Q4000 vessel on the surface. Both the oil and gas captured by this additional system are expected to be flared through a specialized clean-burning system.

 

Driller News

 

Several floating rig owners report that they have reached a “safe stopping point” and have moved their rigs off location or are preparing to do so.  Transocean says the Discoverer Clear Leader is now stacked in Ship Shoal 363 after finishing up in Green Canyon Block 640 for Chevron.  The rig, however, is expected to arrive on location in Mississippi Canyon 252 to join the Discoverer Enterprise as an oil collection vessel for BP.  Transocean also reports the Discoverer Deep Seas drillship and the Discoverer Inspiration, both working for Chevron, have also plugged their wells and are now stacked in Ship Shoal 362 and 361, respectively.  Meanwhile, two other Transocean rigs are now stacked in the Galveston area.  The GSF C.R. Luigs is in Galveston 360 after wrapping up in Green Canyon 653 for BHP Petroleum and the Discoverer Spirit was moved to shallow waters in Galveston A-80 after drilling in Mississippi Canyon 876 for Anadarko.  As previously reported, Anadarko last week declared force majeure on the contract.  Meanwhile, reports are that ENSCO has finished drilling and will soon complete P&A operations with semis ENSCO 8500 and ENSCO 8501 for Anadarko and Noble Energy/Nexen Petroleum, respectively.  However, it is unclear as to what the future plans for the rig are.  While Anadarko said it would maintain its contract for the 8500, discussions continue with Noble/Nexen in regards to the future of the ENSCO 8501.  The ENSCO 8500 was drilling in Green Canyon 903 while the ENSCO 8501 was working in Mississippi Canyon 519.  Noble Drilling says the Noble Amos Runner is now finished on its well for Anadarko in Keathley Canyon 875.  It is believed the rig will be moved to the Galveston area.  Finally, Diamond Offshore completed work on two sublet wells with semis Ocean Confidence and Ocean Monarch.  The Confidence was in Mississippi Canyon 305 for ATP O&G and is now on standby in the Grand Isle area under its contract with Murphy E&P.  The Monarch was working in Garden Banks 959 for Cobalt International, on sublet from Anadarko.  The rig is now in Diamond’s stack location in West Cameron 184.

 

Market reports indicate that well permitting delays are now affecting a larger number of jackups in the Gulf.  Several rig owners and operators report that some idle time between wells is a real possibility.  As of press time, several jackups are now sitting on location waiting to begin work.  Jackup Rowan Louisiana also fell victim to the delays when McMoRan E&P’s permit for its 180-day well in Eugene Island 26 was not approved.  While Rowan has reported the Louisiana now as cold stacked, it remains to be seen what rig will drill the well should McMoRan be able to get its permit.  Rowan also says the Bob Palmer jackup may not be able to move onto Apache’s location in High Island A-376 later this week when leg repairs are finished on the rig.  Jackup Seahawk 2004 is now also idle while the company waits for Bandon O&G to get a well permit for Vermilion 196 approved.  The rig had been working in Eugene Island 199 for Arena Energy.  Seahawk also says the Seahawk 2500 faces potential idle time as the APM permit for Arena Energy’s workover in Main Pass 122 has yet to be approved.  Meanwhile, the ENSCO 99 continues to wait on location in West Delta 45 for Nexen to secure its permit for a sidetrack in the block.  Chevron is also waiting on its permit for a well in Main Pass 298 where the ENSCO 68 is due to work.  However, leg repairs on the rig are now expected to take a few more weeks to complete.

 

Hercules Offshore has received a one-well contract from Tana Exploration using previously idle jackup Hercules 253.  The rig is now under tow to location with work beginning later this week.  With the award, the rig is next available in early July.  Meanwhile, the Hercules 251 completed work for Phoenix Exploration in Chandeleur 43.  The rig is now in Main Pass 59 undergoing maintenance and repairs, and it is understood that Phoenix will work the rig in the block under an exercised contract option once a permit is secured.

 

Service/Supply News

 

Helix Energy Solutions Group announced that its floating production unit, the Helix Producer I (HPI), has been contracted by BP to assist in its oil spill response operations.   The HPI will be part of BP's containment plan to capture and process oil and gas from the Macondo well and to offload such oil and gas to a tanker. The HPI is expected to support BP's efforts for a minimum of sixty days. 

 

June 7, 2010

 

Rig Utilization

 

Mobile rig utilization in the Gulf of Mexico was unchanged this week.  Total fleet utilization is 61.0% with 75 of 123 mobile rigs under contract or committed for work.  Marketed utilization, which excludes those cold stacked and other non-marketed rigs, is slightly higher at 89.3% with 75 of the 84 units under contract.

 

Total jackup utilization is unchanged at 50% with 41 of 82 jackups under contract. One working unit was released due to permitting issues, and another jackup was cold stacked for yet to be determined reasons.  Marketed utilization rose slightly to 83.7% with 41 of 49 rigs contracted.

 

Floating rig fleet utilization for now remains at 94.2% with 33 of 35 floaters under contract, while marketed utilization also stays steady at 97.1% with 33 of 34 units under contract.

 

Platform rig fleet remained at 41.2% with 21 of 51 rigs contracted, while marketed utilization is 55.3%, with 21 of 38 rigs under contract.  Finally, inland barge fleet utilization rose to 48.3% with 28 of 58 units under contract, while marketed utilization jumped to 70% with 28 of 40 units under contract.

 

Headline News

 

The shallow water Gulf of Mexico drilling rig market appeared to get a bit of a reprieve last week when rumors that the deepwater drilling suspension had been extended to include water depths under 500 fsw were proven to be false.  However, despite dodging that bullet, the market did not escape unscathed.  In a June 2 news release, Bureau of Land Management Director Bob Abbey, who has also been put in as the Acting Director of the Minerals Management Service (MMS), announced that all new exploration or development drilling (APD's) in water depths under 500 fsw could continue, but that this drilling must be under a drilling plan that “includes information demonstrating compliance with the new safety standards”, referring to recommendations made in the Presidential Commission on the BP Deepwater Horizon Oil Spill report of May 27.  As a result, a handful of previously approved permits have already been rescinded and must be refilled. The bottom line is that some jackups will undoubtedly see some idle time. 

 

On the surface, it would seem to be just a minor inconvenience.  However, if the suggestion from the proposed May 12 oil spill response legislation is enacted, the time the MMS has to approve exploration plans will increase from 30 to 90 days.  Should this occur, the pain level for rig owners will increase greatly as the number of idle units will go up as will the amount of time they remain idle.  The one saving grace is that all sidetrack and non-drilling operations (APM's) are still allowed to proceed, which will keep some rigs busy.  Reports are that some operators have informed rig owners they will be able to shuffle schedules around and make sure work carries on uninterrupted.  However, this is likely a relatively small group.  There are several smaller operators with rig contracts that simply do not likely have the work readily available that would allow a rig to be retained.  While this may ultimately impact mat jackup owners more since they tend to work for these operators more frequently, no one is immune to feeling some level of pain, but it remains to be seen how it will all play out.  Operators and contractors are still waiting on a follow-up Notice to Lessees (NTL) that will further establish the specific requirements for shelf plans.

 

Anadarko has declared force majeure on two of its deepwater rigs, and the company has said it will maintain a third rig currently under contract.  The company said it would attempt to terminate the contracts on the Noble Amos Runner semi and Transocean drillship Discoverer Spirit, but would keep its contract on the ENSCO 8500 semi in effect.  Since that announcement, however, Noble Drilling released a statement saying it believes the deepwater drilling suspension does not constitute force majeure as it does not prohibit Anadarko from using the rig on a variety of non-drilling activities in addition to the operator’s “deep and diverse portfolio of international properties”.   Meanwhile, the Discoverer Spirit move was considered somewhat of a surprise as the rig was rumored as a potential candidate to move to West Africa for an Anadarko drilling program there.  Speculation as to why Anadarko would terminate the Transocean rig and not the ENSCO semi centers around the day rates of each rig.  The Discoverer Spirit is getting $500,000/day while the ENSCO 8500 rate is only $298,000.  It was also rumored that the ENSCO rig was built with a firm contract in place, meaning Anadarko has a “take or pay” provision where it would have to pay out all of or a large portion of the remainder of the contract if it was canceled.  While it is not known why any of these specific rig decisions were made, the Anadarko announcement is the first direct force majeure declaration to take place since the drilling ban was announced. 

 

Cobalt International recently declared force majeure on Diamond Offshore semi Ocean Monarch, but the company had the rig on a sublet from Anadarko, so the final disposition of that contract as well as the two announced recently are still up in the air.  Clearly, this will not be the last force majeure announcement made.  In fact, rumors are that at least 3 other operators have or shortly will claim force majeure on their contracts, but so far this cannot be confirmed.  However, even if it they have occurred, it is still far too early to know the ultimate outcome.  In general, the eventual impact on drilling contractors will likely involve several stages.  First, there is the drilling moratorium itself.  This is clearly the most important factor that will determine the decisions operators make and their effect on rig owners.  Assuming those issues are settled, then there are the coming safety requirements for rigs and what those will entail.  If, for instance, contractors are allowed to continue operating while whatever equipment required is on order, then they can survive that.  If, however, they are not allowed to work until the upgrades are completed, as one source put it, "we may be dead in the water".  The bottom line is that it remains far too early in the process to know what is going to happen.  Nevertheless, if Noble's response to Anadarko is any indication, the coming weeks and months, needless to say, will be very interesting.    
 

Operator News

 

Pemex reports that between 2010 and 2024 it plans an average annual investment of $22.9 billion (369 billion pesos) in its energy industry.  Of the annual expenditures, approximately $16.9 billion will be spent in the exploration and production sector, with the remainder going toward the gas and petrochemical industry.  The company’s goal is to produce 2.7 Mb/d of oil and 6.3 Bcf/d of natural gas in 2012, increasing that to 3.3 Mb/d oil and 8.0 Bcf/d of natural gas by 2024.

 

BP advises that  the lower marine riser package (LMRP) containment cap, installed on June 3, continues to collect oil and gas flowing from the well and transport it to the Discoverer Enterprise drillship on the surface.  On June 5, a total of 10,500 barrels of oil was collected and 22 mmcf of natural gas was flared.  From June 3-5, the volume of oil collected was 16,600 barrels and 32.7 mmcf of natural gas was flared.

 

Driller News

 

Nabors Offshore platform rigs Super Sundowner XXI is now hot stacked in New Iberia after wrapping up operations for Anadarko in Green Canyon 608.  The rig had been working on a two-well contract since last December.  Chevron also finished up with workover unit Sundowner IV and that rig is now too hot stacked in New Iberia.  Finally, the MODS 150 workover unit will finish up in Garden Banks 668 with Anadarko later this week and also will be mobilized to Nabors facility in New Iberia.  However, the rig will return to the location for an additional well at the end of hurricane season.  Finally, Nabors has secured a four-well plus options contract (pending permit approvals) with Chevron for workover jackup Dolphin 106.  The firm portion of the program should keep the rig busy for around 60 days to late July.  Prior to the contract award, the rig had been idle since March 2009.

 

Spartan Offshore has completed its contract with Mariner Energy and the rig is now hot stacked on location in Eugene Island 53.  The rig was supposed to go next to West Cameron 269 for a 60-day program with Phoenix Exploration, but the permit was rescinded and will now be refiled, so the rig will be idle in the meantime.  The company has a 30-day well for Century Offshore scheduled for the rig, but it is understood the company will not be ready to begin for awhile yet.  Meanwhile, the Spartan 202 is now moving to Eugene Island 123 for a 20-30 day program with Marlin Energy.  The rig just completed a workover for Pisces Energy in South Timbalier 204.  Hilcorp Energy has picked up the Spartan 208 for a two-well deal in Vermilion 39.  The first well is due to last around 30 days, and while the second location does not yet have an approved permit, it is believed that will occur by the time the rig is ready to move.  Finally, the Spartan 303 will wrap up its contract in West Cameron 132 with Marlin Energy this week.  Spartan is talking to multiple operators about follow-up work, but reports are that none have permits in place, meaning the rig may very well see a bit of idle time until work is secured.

 

Diamond Offshore jackup Ocean Spartan moved to location in South Timbalier 179 over the weekend for the start of a newly awarded four-well contract with Nippon Oil.  The rig had been scheduled to drill the second of a two-well contract for Shell in the Mobile Bay area, but was hot stacked in West Cameron 184 after the operator opted not to proceed.  The new deal should keep the rig busy for about 60 days to early August.

 

Jackup ENSCO 99 completed its contract with ExxonMobil in Grand Isle 16 and moved late last week to its next contract, Nexen Petroleum's location in West Delta 45 for a 30-45 day sidetrack well.  While rigging up on location, however, Nexen's previously approved well permit was rescinded, leaving the operator scrambling.  At press time, no decisions regarding what the rig will do had been made and it is currently waiting on location while a solution is found.

 

Rowan reports that the Rowan Louisiana has been cold stacked in Sabine Pass after it finished its one-well program for ERT in Eugene Island 302.  The rig was next scheduled to work for McMoRan Exploration in Eugene Island 26, but it is unclear whether permitting or other issues has caused the rig to go idle.  The rig joins the Rowan Juneau and the Rowan Alaska as cold stacked in the U.S. Gulf.

 

Service/Supply News

 

Bollinger Shipyards, Inc. has received safety awards from the Shipbuilders Council of America and the National Safety Council.

 

The Gas Technology Institute awarded George P. Mitchell, former Chairman of Mitchell Energy & Development Corporation, with a lifetime achievement award for pioneering drilling and completion technologies that revolutionized drilling in gas shales.

 

June 1, 2010

 

Rig Utilization

 

Mobile rig utilization in the Gulf of Mexico fell slightly this week as several fleet changes occurred.  One semi left the region while two drillships are now enroute to the area.  Total fleet utilization is 61.0% with 75 of 123 mobile rigs under contract or committed for work.  Marketed utilization, which excludes those cold stacked and other non-marketed rigs, is virtually unchanged at 88.2% with 75 of the 85 units under contract. 

 

Total jackup utilization is unchanged 50% with 41 of 82 jackups under contract, while marketed utilization is 82% with 41 of 50 rigs contracted.

 

Floating rig fleet utilization is at 94.2% with 33 of 35 floaters under contract, while marketed utilization is now 97% with 33 of 34 units under contract.  Pride’s newbuild ship Deep Ocean Ascension arrived here while Transocean’s Deepwater Pathfinder is now enroute.  One drillship inadvertently left out of the fleet was added back into the numbers.  Meanwhile, Diamond Offshore’s Ocean Baroness and Transocean’s Cajun Express both left the Gulf for international work.

 

Within the platform rig fleet, utilization rose slightly with 21 of 51 rigs contracted for utilization of 41.2%, while marketed utilization is 55.3%, with 21 of 38 rigs under contract.  Finally, inland barge fleet utilization rose to 43.1% with 25 of 58 units under contract, with marketed utilization is 62.5% with 25 of 40 units under contract.

 

Headline News

 

In a move that could be considered the worst case scenario, the Obama Administration has extended the deepwater moratorium on permitting established after the Deepwater Horizon blowout and canceled the upcoming Western Gulf lease sale.  However, the bigger blow came when it was also ordered that current deepwater drilling be suspended for six months until the six-month investigation into the accident is completed.  Operations are to be halted as soon as the first safe stopping point can be reached and the well secured.  Some reports indicate that non-drilling operations like completions, P&A’s and workovers may be allowed, but even that is unknown for now.  As for the ruling, it will directly affect 23 semis and 10 drillships currently working or scheduled to work in the Gulf of Mexico as well as the vast number of ancillary services that support deepwater drilling.  It is expected that most of the rigs will reach the “safe stopping point” within the next few weeks, the real question is then what?  So far, three rigs (drillships Discoverer Clear Leader and Discoverer Deep Seas and semi West Sirius) were already on standby due to the permitting moratorium, and one contract has been ended. 

 

Marathon Oil has finished P&A operations on its well in Mississippi Canyon 993 with the Noble Paul Romano semi and has released the rig.  Meanwhile, Cobalt International has declared force majeure on its contract for Diamond Offshore semi Ocean Monarch, believed to be the first such occurrence.  The rig had just moved onto location in Garden Banks 959 a week ago, but had not begun drilling operations.  The wrinkle here is that Cobalt has the rig on a sublet from Anadarko, so how the force majeure will work is not yet clear.  It is believed that Diamond is preparing to move the rig to its stack location in West Cameron 184.  So, focusing on the other 31 floaters, the majority of these are working for operators that could offer an alternative in another part of the world.  However, assuming these alternative wells exist, they could be already slated for another rig or they may not be able to get the locations ready for drilling in a reasonable amount of time.  So while the operators working these rigs will no doubt attempt to move them when and where they can, this scenario will likely not save every contract. 

 

What about the other rigs working for smaller operators?  These are the companies that typically have limited or no exposure to international markets.  With these companies, a few possibilities exist.  One is that they keep the rig on a greatly reduced standby rate, perhaps just its operating cost.  However, this is $100,000 per day or more so paying that kind of money for six months with essentially nothing to show for it is a questionable proposition at best.  After that, it may very well come down to declaring force majeure and canceling the contract as in the case with Cobalt.  While no one likes to think about having to do this, it has to be considered a very real possibility for this group of rigs.  It should be noted that Devon Energy is included in this group due to the fact that the company recently sold its GOM deepwater assets and would likely welcome being able to get out of its rig obligations.  It was rumored that the company was close to securing a sublet that actually would take the rig in question to an international market, so the status of that is now up in the air.  Nevertheless, each contract is different and each has different force majeure language in it.  Generally, the operator will be responsible for some day rate for a specified period before the contract is officially terminated.  One thing that is safe to say is that the legal departments for both contractors and operators will be busy over the coming weeks and months.  At this point, no one knows what will ultimately happen, but no matter what happens, the impact of this suspension will most definitely extend into international markets, particularly in regards to day rates.  With the increase in supply to some markets, the rate structures, already falling, will now do so even further.  The operators will reap the benefits of lower rates, and the contractors will get to keep their rigs working, albeit most likely for less money.  In the meantime, the cost of drilling in the Gulf of Mexico for both operators and drilling contractors will be going up in the future. 

 

The permitting/drilling ban coincided with new drilling regulatory requirements and recommendations made in the 30-day Safety Report produced by Secretary of the Interior Ken Salazar.  This report recommends a number of specific measures that are designed to enhance the safety of offshore drilling.  The report calls for among other things that all BOP equipment used on floating rigs be re-inspected and independently recertified and that within one year all operations require two sets of blind shear rams on BOP’s to further prevent system failure during an emergency.  Further measures will be addressed within the next 120 days and working groups will be formed to make other recommendations as well.  Most likely, when all the dust has settled, some smaller operators will likely reconsider their desire to participate in the deepwater arena, but others will realize the importance of the market and will simply wait for the six months and then resume drilling.  However, it remains to be seen what the rig fleet here will look like in six months in addition to whether a sufficient number of personnel will be available to man them.  While some rigs might be taken overseas for a few wells and then brought back, it is more likely that those leaving will not be returning for awhile.  In the long run, it is possible that rigs leaving would eventually benefit this market, but it is far too early to tell what the final impact of any of this will be.

 

Operator News

 

Pemex opened bids on May 26 for four jackup contracts.  In Parts 1, 2 and 4, Perforadora Central, as expected, was the low bidder for all three programs, comfortably outbidding Geomarex and ISO/Aban Offshore for the work.  In Part 1, Perforadora bid its Tuxpan jackup for the 430-day program with a total bid amount of $44,163,500.  Drilling is scheduled to begin October 28, 2010.  The rig has been idle at the Keppel AmFELS yard in Brownsville since it was delivered earlier this year, so an early start to the contract could occur.  In Part 2, a 256-day program also starting October 28, 2010, Perforadora was the low bidder with the Panuco with a total bid of $28,536,000.  In Part 4, Perforadora submitted a total bid of $32,352,000 using the Tonala jackup.  The 292-day contract is scheduled to begin December 1, 2010.  Finally, in Part 3 of the package, Noble Drilling submitted the low bid of $18,629,001 with jackup Noble Roy Butler.  The 254-day program is due to begin December 19, 2010.  However, the rig is currently working for Pemex, with the contract scheduled to end around mid-July.  It is expected that Noble will either continue to receive extensions that will keep it working up until the start date, or Pemex will simply begin the contract early.  A decision could be made by the time the official awards are made on June 12.  Noble has also received requests for and expects to soon receive extensions for several other of its jackups currently working for Pemex.  The contractor anticipates receiving close to a five-month extension for the Noble Bill Jennings starting when the current contract ends on June 17.  The new term would keep the rig under contract to November 10.  Noble also reports a likely 73-day extension for the Noble Eddie Paul when the current contract ends June 3.  Pemex is also expected to extend its contract on the Noble Leonard Jones on a direct assignment basis for another 70 days starting June 22, keeping the rig busy to August 31.  The Noble Gene Rosser is expected to get a six-month extension to mid-December when its current term wraps up June 20.  The Noble John Sandifer is expected to receive a 93-day extension starting June 17.  All of the above are subject to day rate agreement, but these additional terms should get done.  Finally, the Noble Lewis Dugger began a 142-day extension on May 29 that now keeps the rig busy to October 18.

 

BP advised that the latest technology being used to stop the deepwater oil leak includes the deployment of a lower marine riser package (LMRP) cap containment system. ROVs are engaged in preliminary operations, including preparing for operations to cut through and separate the damaged riser from the LMRP at the top of the Deepwater Horizon’s failed blowout preventer (BOP).

 

Shell reportedly will not take Diamond Offshore jackup Ocean Spartan to its Mobile Bay location for the second well of its two-well contract.  While Shell will pay Diamond for the 40-day term, the rig now remains stacked and is now available in West Cameron 184.  Meanwhile, reports are that Chevron will soon extend its contract on jackup Ocean Columbia through the end of 2010.  The operator recently extended jackup contracts with ENSCO and Hercules Offshore for the remainder of the year.  Rumors also are circulating that ANKOR Energy may have further work in store for jackup Ocean Titan.  The rig is currently working under a 90-day extension that ends in mid-June.

 

Driller News

 

Hercules Offshore has secured a one-well contract with Newfield Exploration.  Jackup Hercules 257 is getting on location in West Delta 72, with tie-back and completion work expected to take 30 days.  The rig had been working for Energy XXI in South Timbalier 21. 

 

Rigs on the Move...

 

Jackup Rowan EXL-1 is headed to High Island A-531 to plug a well for McMoRan E&P after sitting in Sabine Pass since its delivery due to the ongoing permitting issue. McMoRan is expected to have a permit in place soon for a 50-day sidetrack in the block.  It is then scheduled to move to West Cameron 294 for a 30-day sidetrack, followed by a 140-day drill well in Eugene Island 223.  Inland barge Parker 72-B completed its contract with Davis Petroleum off Galveston and the rig has been moved to Parker’s dock in New Iberia.  However, it is expected that the rig will begin a new contract later this week.  Details will be reported once the contract is signed.

 

Service/Supply News

 

FMC Technologies, Inc. appointed Johan F. Pfeiffer as Vice President, Global Surface Wellhead.